Project’s Phases
Total budget : 3.519.615 lei
Total public funding: 2.990.000 lei
Co-financing: 529.615 lei
Duration of the project: 4 years
Phase 1: Services requirements and definition
Objectives:
- Collecting the users requirements, defining the service technical specifications and algorithms’ development.
Deliverables foreseen at the end of the phase:
- Users requirements document.
- Technical specifications document.
- Services architecture document.
- Algorithms description document.
- Principle Investigator proposal submitted to DLR (TerraSAR-X) or CSA (Radarsat-2).
- Document with the description of the test site and cross-validation GPS references.
- A set of test cases and harnesses used to test each software routine.
Phase duration: month 0-6 of the project.
Phase 2: Service processing chains preliminary design
Objectives:
- To develop preoperational service, to streamline the developed algorithms and to process dataset.
Deliverables foreseen at the end of the phase:
- Preoperational CIMS, SIMS and SMMS.
- TOPSAR simulation algorithm and results.
- Preliminary products: ground deformation maps and radar targets deformation profiles.
- TOPSAR coregistration.
Phase duration: month 7-18 of the project.
Phase 3: Prototype services implementation
Objectives:
- To refine the products and to develop and implement the prototype services.
Deliverables foreseen at the end of the phase:
- Natural hazards and seismic scenarios for Cernavoda zone.
- PSI two dimensional deformation profiles.
- TOPSAR resampling algorithm.
Phase duration: month 9-30 of the project.
Phase 4: Prototype services validation and demonstration
Obiectives:
- To validate the prototype services, to integrate the users’ feedback and to train the users.
Deliverables foreseen at the end of the phase:
- Refined products (v1).
- A refined structural stability model for Cernavoda NPP.
- Information on different kinds of soil deformations (v1).
- SENTINEL-1 interferogram and statistical analysis of the coregistration accuracy.
Phase duration: month 31-36 of the project.
Phase 5: Final validation, training, dissemination
Obiectives:
- Final validation of the prototype services.
Deliverables foreseen at the end of the phase:
- Prototype services CIMS, SIMS and SMMS.
- Refined products (v2).
- Information on different kinds of soil deformations (v2).
- Validation documentation.
- Training materials.
Phase duration: month 37-48 of the project.